add to favorites contacts sitemap
REPAIR MAINTENANCE OPERATION OF MOTOR VEHICLES
Jeep Grand Cherokee (from 1993 to 1999, the year of issue)

general info. full specifications. diagnostics. hints. tips. tricks
Jeep Grand Cherokee
Home
 
Jeep
Grand Cherokee
Introduction
Adjustment and routine maintenance
The straight six-cylinder engine
The V8 engine
Procedure of the general and engine major repairs
general information
Overhaul of the engine - the general information
Check the compression pressure in the cylinders
Diagnostic Tests produced using gauge
Methods for removal of the engine and the necessary precautions
Removing and installing engine
Recovery Options Engine
An order of dismantling of the engine
Dismantling of a head of cylinders
Cleaning and checking the status of a head of cylinders
Service valves
Assembling the cylinder head
Removing the connecting rod and piston assembly
Removing the crankshaft
Cleaning the engine block
Checking the engine block
Honing cylinders
Checking the connecting rod and piston assembly
Checking the status of the crankshaft
:20. Checking the main and connecting rod bearings
The order of assembly of the engine after completing its overhaul
Installation of a cranked shaft and check of backlashes of radical bearings
Installation of the piston rings
Installing the connecting rod and piston assembly and check of backlashes in the connecting rod bearing
The first start of the engine after major repairs
Systems of cooling, heating and air conditioning
The power supply system and exhaust
The system of electric motor
Systems of decrease in toxicity of the fulfilled gases and engine management
Manual box of a gear change
Automatic Transmission
Transfer Case
Clutch and transmission line
Brakes
Suspension and steering
Body
The system of on-board electrical equipment
Controls and operation receptions
 


Hit Counter by Digits


print page printable version

The order of assembly of the engine after completing its overhaul



Before assembling the engine, make sure you have all the necessary parts, gaskets, seals, as well as the following tools and materials:

  • The usual set of plumbing tools
  • Socket wrench with drives by 1/2 and 3/8 inch (9.5 and 13 mm)
  • The tool for removal / installation of piston rings
  • The tool for compression of piston rings
  • Tool to install vibration damper
  • Short lengths of rubber or plastic hose for putting on the bolts connecting rod bearing caps to protect against damage to cylinder bores and crankshaft journals
  • Set to measure the gaps in the bearings by means of the calibrated plastic wire (Plastigage)
  • Set the blade-type probe
  • Files with a fine tooth
  • Fresh engine oil
  • The assembly or molybdenum grease
  • Gasket Sealant
  • Sealant Threadlocking

To save time and reduce problems arising from the engine assembly should be done in the following order:

  • New camshaft bearings (set in the workshop of car-care center)
  • Piston rings
  • Crankshaft and main bearings
  • The connecting rod-piston assembly
  • Oil pump
  • The camshaft and hydraulic lifters
  • Sump
  • Cylinder head
  • Distribution chain with asterisks
  • Head (s) of the cylinders, rocker arms and pushrods
  • Cover the distribution chain
  • Intake manifold and exhaust manifold (s)
  • The cover (s) of the head (s) of the cylinders
  • Flywheel / drive plate




« previos page
:20. Checking the main and connecting rod bearings
next page »
Installation of a cranked shaft and check of backlashes of radical bearings