add to favorites contacts sitemap
REPAIR MAINTENANCE OPERATION OF MOTOR VEHICLES
Mercedes-Benz G-Class (W463, 1999 issue)

general info. full specifications. diagnostics. hints. tips. tricks
Mercedes-Benz G-class
Home
 
Mercedes-Benz
G-class
Introduction
Controls and operation receptions
Current care and maintenance
Engine
System of cooling, heating, ventilation and air conditioning
The power supply system and exhaust
General information and safety measures
The power supply system of petrol engines
The power supply system of diesel engines
Exhaust systems and reduce emissions
general information
Removing and installing exhaust system
Removal and installation of final collectors
Removing and installing Lambda probe
Removal and installation of an air pump
Removal and installation of the valve purge of a coal adsorber (EVAP)
Removal and installation of a coal adsorber (EVAP)
Removing and installing the EGR valve
Removal and installation of the EGR cooler
Removing and installing positioners EGR
Removing and installing coolant temperature sensor (CDI)
Systems of an electric motor
Automatic Transmission
Transmission Line
Brakes and auxiliary systems
Suspension and steering
Body
Onboard electric
Wiring
 


Hit Counter by Digits


print page printable version

Removal and installation of the EGR cooler



Diesel models

Models 463.323 (M612)

Details of installation of the EGR cooler models 463.323 (1 of 2)

1, 2, 3 - Hoses cooling path
4 - Vacuum line
5 - Cover
6 - Installation of heating fuel
7 - EGR cooler

8, 10, 13, 15 - Bolts
11 - Hollow bolt couplings
12 - the fuel return line
14 - Bracket

Details of installation of the EGR cooler models 463.323 (2 of 2)

16 - Exhaust


PERFORMANCE ORDER

  1. Drain the cooling system (see chap. Current care and maintenance).
  2. Remove the trim panel of the cylinder head cover.
  3. Disconnect hoses cooling path (1, 2 and 3).
  4. Disconnect vacuum line (4), take it with a fixing clamp to the side and remove the cover (5).
  5. Loosen the bolt (8) on the bracket (9), unscrew the bolt (10) and disconnect from the cooler (7) fuel heating device (6).
  6. Remove banjo bolt couplings (11) securing the fuel return line (12) to the fuel line.
  7. Remove the bolts (13) the bracket (14) and the cooler (7). Remove the bracket (14).
  8. Otboltite from the cylinder head and the exhaust system (16) and remove the cooler (7).
  9. Installation is performed in reverse order - do not forget to replace the sealing elements.
  10. Finally, check the components of the power and cooling of the engine for signs of leaks.

Models 463.333 (M628)

Details of installation of the EGR cooler models 463.333 (1 of 2)

1 - Fuel filter
2 - Connection pipe
2a, 2c, 3a, 3c, 3d, 4a, 4c, 4d, 7 - Bolts
2b, 3b, 4b - Gaskets
3 - The top right section of the diffuser
4 - left upper section of the diffuser
5 - Left intermediate duct

6 - Right intermediate duct
8 - EGR cooler
9 - Vacuum units drive off the intake ports
10 - activator of the throttle to the upper airways
13 - Right air intake duct
14 - Panel finishes oil filler cap

Details of installation of the EGR cooler models 463.333 (2 of 2)

11, 12 - Connecting pipes
A - The direction of removal of the coolant

B - Direction removing cooler

PERFORMANCE ORDER

  1. Remove protection crankcase.
  2. Drain the cooling system (see chap. Current care and maintenance).
  3. Remove the air cleaner (see. Section Service Component inlet air path).
  4. Remove the right air intake duct (13) (see. Section Service Component inlet air path).
  5. Remove the oil filler cap trim (14).
  6. Remove the fuel filter (1), - the filter must be replaced without fail.
  7. Remove the left and right air intakes complete with sensors MAF (see. Section Service Component inlet air path).
  8. Remove the throttle actuator assembly with the upper airways (10) (see. Section Service Component inlet air path).
  9. Remove the valve assembly (see. Section Removal and installation of the valve assembly).
  10. Remove positioner EGR (see. Section Removal and installation of positioners EGR).
  11. Remove the bolts (2a and 2c), and remove the right connecting pipe (2). Prepare replacement gaskets (2b).
  12. Remove the screws (3a, 3c and 3d) and remove the top half of the right-hand section of the diffuser (3). Prepare replacement gaskets (3b).
  13. Remove the bolts (4a, 4c and 4d) and remove the upper half of the left-hand section of the diffuser (4). Prepare replacement gaskets (4b).
  14. Disconnect the vacuum hose from the vacuum units (9) off the left and right intake ports.
  15. Remove the bolt (7) and assembly otboltite vacuum blocks (9) light-off of the left inlet port of the diffuser.
  16. First, pull up the back side (A) cooler EGR (8), and then post it back toward the front (B) and remove the cooler (7) with connecting pipes (11 and 12). If necessary, prepare the removable sealing ring.
  17. Installation is in the reverse order.