add to favorites contacts sitemap
REPAIR MAINTENANCE OPERATION OF MOTOR VEHICLES
Jeep Grand Cherokee (from 1993 to 1999, the year of issue)

general info. full specifications. diagnostics. hints. tips. tricks
Jeep Grand Cherokee
Home
 
Jeep
Grand Cherokee
Introduction
Adjustment and routine maintenance
The straight six-cylinder engine
The V8 engine
Procedure of the general and engine major repairs
Systems of cooling, heating and air conditioning
general information
Antifreeze - the general information
Check of functioning and thermostat replacement
Check of serviceability and replacement of the cooling fan and clutch his clutch
Check the operation and to replace the coolant temperature sensor
Removing and installing radiator and cooling system expansion tank
Check operation of the water pump
Removal and installation of the water pump
Check of an electric circuit and replacing the motor fan heater and air conditioner
Removal and installation of the unit heater fan
Removal and installation of assemblage of the control heater and air conditioner
Removing and installing heat exchanger heater
Check of serviceability and maintenance of heating systems and air-conditioning
Diagnosis of automatic temperature control (ATC) without removing it from the car
Removing and installing battery (accumulator) air conditioning system
Removal and installation of the air conditioning system compressor
Removal and installation of air conditioning condenser
Removal and installation of a calibrated nozzle tube
Removal and installation of evaporator air conditioning system
The power supply system and exhaust
The system of electric motor
Systems of decrease in toxicity of the fulfilled gases and engine management
Manual box of a gear change
Automatic Transmission
Transfer Case
Clutch and transmission line
Brakes
Suspension and steering
Body
The system of on-board electrical equipment
Controls and operation receptions
 


Hit Counter by Digits


print page printable version

Removing and installing heat exchanger heater



See. The warning at the beginning of Section Removal and installation of the unit heater fan.


The air conditioning system is constantly under pressure. Do not loosen the couplings of lines or disconnect any of the components of the system prior to its discharge. Coolant must be pumped out of the system in a special compensatory and regenerative EPA-unit station dealer branch or an authorized service center. When disconnecting the lines of the system, always wear safety goggles!

Withdrawal

Repair exchanger heater car Jeep Grand Cherokee is a difficult task that lies outside the qualification of the average mechanic-fan work should be done very carefully, without haste. Many of the fittings and electrical connections of the system are located deep under the dashboard, and access to them is very limited. To remove the unit from the car heater / air conditioner must remove the entire dashboard.


PERFORMANCE ORDER

  1. On models equipped with air conditioning, make a discharge system (see. The warning above).
  2. Disconnect the negative wire from the battery.
  3. Drain the cooling system (Head of Adjustment and routine maintenance) and disconnect the hoses from the inlet and outlet of the heat exchanger heater fittings.
  4. Remove console lower steering column assembly and remove the dashboard (Section Body).
  5. Disconnect the electric heater fan motor connector (Section Removal and installation of the unit heater fan).
  6. On models equipped with air conditioning, disconnect the line from the evaporator system bulkhead engine compartment. To disconnect fittings require special clamps.
  1. To stretch the ring spring when disconnecting lines of air-conditioning system is necessary to use a special tool.
  1. Remove the expansion tank (see section Removing and installing radiator and expansion tank of cooling system).
  2. Remove the engine compartment bulkhead processor (PCM), not disunite 60-terminal electrical connector.
  3. PCM Pull far enough to give the fastening nut block heater / air conditioner (three behind the processor, one - above the distributor on models with engine V8) from the studs on the side facing the engine side of the bulkhead of the engine compartment.
  1. Give nuts on the motor housing side of the bulkhead compartment.
  1. Mark and disunite electric sockets for heater / air conditioner and fan motor resistor assembly. Disconnect the vacuum hose from the vacuum motor.
  2. Remove the drain tube evaporator.
  3. Remove the sleeve blowing glass (on the block heater / air conditioner).
  1. Disconnect the hose heating rear foot wells.
  1. Give nuts from the studs to the reverse side of the cabin bulkhead engine compartment and take assemblage of a heater / air conditioner out of the car.
  2. Give fixing screws and remove the coil heater by pulling it straight up out of the housing.
  1. The heat exchanger heater is removed from the housing for heater / air conditioner.

Setting

PERFORMANCE ORDER

  1. Install a heat exchanger in a casing of a heater / air conditioner and replace the screws.
  2. When you install CONNECT exchanger gasket for fixing it during the installation of the fan assembly.
  3. The installation of the remaining components are produced in the reverse order of their removal.

When installing the fan cowl / evaporator careful not to pinch the wires between the housing inlet and the instrument panel on the right side of the housing.

  1. Fill the cooling system.
  2. Make evacuation, recharge and check for leakage of the air conditioning system (if any).
  3. Start the engine and check that its operation.




« previos page
Removal and installation of assemblage of the control heater and air conditioner
next page »
Check of serviceability and maintenance of heating systems and air-conditioning